Expansion of the Salerno-Reggio Calabria railway line

Expansion of the Salerno-Reggio Calabria railway line

This project involves the construction of a new railway line with High Speed characteristics for the Salerno-Reggio Calabria track, constituting a strategic passenger and freight route connecting the north and south of the country.

There are also plans to build several stops along the new line and to double the Paola-Cosenza section through the new Santomarco Tunnel in order to upgrade the freight route to the Port of Gioia Tauro. The interventions will ensure greater accessibility to the railway system and the possibility of developing new passenger traffic along the north-south axis of the peninsula, which would also benefit connections to and from Sicily. 

The entire route from Salerno to Reggio Calabria was divided into functional Lots. Considering the size and cost of the entire project, the study carried out identified possible intermediate scenarios in terms of time, defining amongst the various Lots the priorities that would produce the greatest benefits for the route.

Vera Fiorani was appointed Extraordinary Governmental Commissioner for completion of the works.

Advantages

  • Upon completion of the entire project, a reduction in the Rome-Reggio Calabria journey time of up to 4 hours depending on the operating model, beyond 2026.
  • The new infrastructure will this facilitate the development of new passenger traffic along the north-south axis of the peninsula, also benefiting the connections to and from Sicily.
  • The infrastructure will allow for the increase of freight traffic in supply to the port of Gioia Tauro.
acav
2-300 km/h maximum speed
207 total kilometres
13.045 mld € in investments

Work progress status

  • Design
    Since 2021
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work
    Dal 2023
  • End of work
    Since 2026

Battipaglia - Romagnano - Lot 1a Battipaglia - Romagnano

Stages of progression: WORKS

  • Design end date: 2021
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Activation Date: december 2026

Romagnano - Praja - Lot 1b Romagnano - Intermediate stop and Lot 1c intermediate stop – Praja

Stages of progression: PERMITS

  • Design end date: 2022
  • Activation Date: dicembre 2030

Doubling galleria Santomarco - Doubling tunnel Santomarco (Paola - Cosenza)

Stages of progression: PERMITS

  • Design end date: 2021
  • Activation Date: december 2029

Praja Paola - Lot 2 Praja Paola

Stages of progression: DESIGN

  • Activation Date: december 2030