Rome-Pescara line

Rome-Pescara line

This project sees significant infrastructural and technological enhancement works along the Rome-Pescara line, split into several phases and aimed at improving mobility between Lazio and Abruzzo. Doubling, speeding up and upgrading will reduce journey times from the current 3 hours and 20 minutes to around just 2 hours.

Vincenzo Macello was appointed Extraordinary Governmental Commissioner for completion of the works.

Advantages

  • Reduced travel time, from Rome to Pescara in about 2 hours compared to the current 3 hours and 20 minutes, with a shorter travel time up to 80 minutes (upon completion of the entire project);
  • Increased capacity – from 4 to 10 trains/hour on the sections being doubled, with the possibility of establishing metropolitan services between Chieti and Pescara;
  • Acceleration and adjustment of the connections between Pescara and L'Aquila, thanks also to other ongoing and scheduled interventions on the L’Aquila-Sulmona line (Bretella Sulmona, a new Sulmona Santa Rufina stop);
  • A performance adjustment to facilitate the development of freight traffic.

 

av
200 km/h Maximum speed
52 total kilometres
7,318 mld € in investments

Work progress status

Following are the details of the progress of works on the Rome-Pescara line.
  • Design
    Since 2019
  • Permits
    Since 2020
  • Tenders
    Since 2020
  • Start of works
    Since 2021
  • End of works
    Since 2025

Bretella railway link for Sulmona - Bretella railway link for Sulmona

Stages of progression: WORKS 

  • Design end date: 2019
  • End date of the authorisation process: 2020
  • Date of tender publication: 2020
  • Start date of executive design and implementation: 2021
  • Work end date: 2024
  • Activation date: December 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 0 - C onstruction III tracks Pescara PN - Pescara C.le

Stages of progression: DESIGN 

  • Activation date: June 2030

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 1 - Pescara PN - San Giovanni Teatino

Stages of progression: PERMITS 

  • Design end date: 2022
  • Activation date: June 2030

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 2 - San Giovanni Teatino - Chieti

Stages of progression: PERMITS 

  • Design end date: 2022
  • Activation date: May 2028

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 3 - Chieti - D’Abruzzo Interport

Stages of progression: PERMITS 

  • Design end date: 2022
  • Activation date: August 2027

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 4 - PRG and ACC for Chieti

Stages of progression: PERMITS 

  • Design end date: 2021
  • Activation date: May 2028

Strengthening Roma - Pescara - Lot 1 - D’Abruzzo Interport - Manoppello

Stages of progression: WORKS

  • Design end date: 2021
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Activation date: December 2026

Strengthening Roma - Pescara - Lot 2 - Manoppello - Scafa

Stages of progression: WORKS

  • Design end date: 2021
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Activation date: December 2026

Strengthening Roma - Pescara - Lot 3 - Sulmona - Pratola Peligna

Stages of progression: DESIGN 

  • Activation date: December 2027

Strengthening Roma - Pescara - Lot 4 - Tagliacozzo - Avezzano

Stages of progression: DESIGN