Expansion of the Venice - Trieste line

Expansion of the Venice - Trieste line

On the Venice-Trieste line, the project envisages the realisation of a series of operations concerning the technological upgrading of the Mestre-Ronchi Sud section, the elimination of a range of level crossings, interventions on the line structures, two new Signalling Controls, plus track variants in Portogruaro, Latisana, along the Isonzo River and between Ronchi dei Legionari and Aurisina. Through these interventions, increasing the speed of the line to 200 kilometres/hour is also planned. 

For commuter and tourist users, the benefits produced by such operations will be a reduction in journey times, an increase in capacity and regularity of operation, along with the improved performance of the line in terms of long-distance traffic, set to allow it to be brought up to European standards for freight corridors. 

Vincenzo Macello was appointed Extraordinary Governmental Commissioner for completion of the works.

av
200 km/h maximum speed
161 total kilometres
1,800 mld € in investments

Work progress status

  • Design
    Since 2019
  • Permits
    Since 2020
  • Tenders
    Since 2020
  • Start of work
    Since 2021
  • End of work
    Since 2026

Variant Rochi-Aurisina - Variant Rochi-Aurisina

Stages of progression: DESIGN

 

Variant Isonzo and Portogruaro - Variant Isonzo e Portogruaro

Stages of progression: PERMITS

  • Design end date: 2021

Variant Latisana - Variant Latisana

Stages of progression: SUSPENDED

Historical line - Historical line technological upgrade

Stages of progression: WORKS

  • Design end date: 2019
  • End date of the authorisation process: 2020
  • Date of tender publication: 2020
  • Start date of executive design and implementation: 2021
  • Work end date: 2026
  • Activation Date: june 2026

Removal of D4 axial weight limitation - Removal of D4 axial weight limitation

Stages of progression: DESIGN

  • Activation Date: december 2026

Priority level crossing elimination - Priority level crossing elimination

Stages of progression: PERMITS

  • Design end date: 2022
  • Activation Date: december 2026

Level crossing elimination completed - Level crossing elimination completed

Stages of progression: PERMITS

  • Design end date: 2022
  • Activation Date: tbd