Development of the Orte-Falconara

Development of the Orte-Falconara

The project aims to strengthen the passenger connection between the Tyrrhenian and Adriatic regions and to create an alternative freight route for north-south connections. The works, broken down into several stages, consist in doubling mainly as a track variant of certain sections of the Orte-Falconara Apennine transversal.

Vincenzo Macello was appointed Extraordinary Governmental Commissioner for completion of the works.

Advantages

  • Upon completion of the operations, the possibility to achieve a reduction in travel times between Rome and Ancona for some services by up to about 30 minutes and between Rome and Perugia by up to about 15 minutes in relation to the operating model and the completion of the Spoleto-Terni doubling.
  • Improvement of the levels of regularity thanks to a review of the operating model that derives from the new infrastructural configuration and the different programming of services, also in relation to the completion of the Spoleto-Terni doubling.
  • Increased capacity – from 4 to 10 trains/hour on the entire line.
  • Improvement of the conditions of accessibility to the service.
  • Performance adjustment to allow the transit of freight trains.

 

av
200 km/h maximum speed
163 total kilometres
4,378 mld € in investments

Work progress status

  • Design
    Since 1999
  • Permits
    Since 2000
  • Tenders
    Since 2013
  • Start of work
    Since 2020
  • End of work
    Since 2024

Doubling Terni - Spoleto - Doubling Terni - Spoleto

Stages of progression: DESIGN

Strengthening Orte-Falconara - Doubling Spoleto – Campello

Stages of progression: WORKS 

  • Design end date: 1999*
  • End date of the authorisation process: 2000*
  • Date of tender publication: 2018*
  • Start date of executive design and implementation: 2020
  • Work end date: 2024
  • Activation date: since september 2024

 

* It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations  

Orte-Falconara: Doubling Spoleto – Campello - Doubling Spoleto – Campello: SSE Spoleto

Stages of progression: DESIGN 

  • Activation date: since November 2024

Doubling Foligno-Fabriano - Doubling Foligno-Fabriano

Stages of progression: DESIGN

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 1 PM228-Genga

Stages of progression: PERMITS 

  • End date of design: 2022

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 2 Genga-Serra S.Quirico

Stages of progression: TENDERS

  • End date of design: 2021
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Activation date: since December 2026

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 3 Serra S. Quirico-Castelplanio

Stages of progression: DESIGN

  • Activation date: since December 2027

Acceleration Orte-Falconara line - Acceleration Orte-Falconara line

Stages of progression: DESIGN

  • Activation date: since December 2026

Doubling PM228 - Albacina - Doubling PM228 - Albacina

Stages of progression: PERMITS 

  • Work end date: 2021
  • Activation date: since December 2026

Falconara Junction variant: SP01 - Falconara Junction variant: SP01 - Falconara Junction 1st phase (Falconara variant)

Stages of progression: WORKS 

  • Design end date: 2011
  • End date of the authorisation process: 2012
  • Date of tender publication: 2013
  • Start date of executive design and implementation: under definition
  • Work end date: under definition
  • Activation date: since December 2024

Falconara Junction variant: SP04 - Falconara Junction variant: SP04: Falconara Junction - Montemarciano - 2nd phase

Stages of progression: DESIGN 

  • Activation date: since August 2026