Palermo Ring Railway

Palermo Ring Railway

The intervention is divided into two functional phases: the first consists in the extension of the current single track Palermo Notarbartolo - Giachery line to the new station called Politeama and, subsequently, in the closure of the ring from the Politeama station to the Palermo station Notarbartolo.​

The second phase involves the construction of the new Turrisi Colonna stop and the transformation of the Politeama station into a stop.​

The project's design phase has received public funding.

Christian Colaneri was appointed Extraordinary Governmental Commissioner for completion of the works.

85 km/h maximum speed
2 total kilometres
142 mln € in investments

Work progress status

Following are the details of the progress of works on Palermo Ring Railway.
  • Design
    Since 2020
  • Permits
    Since 2023
  • Tenders
    .
  • Start of work
    Since 2024
  • End of work
    2028

Palermo ring railway - Palermo ring railway

Stages of progression: TENDERS 

  • Design end date: 2020
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Activation Date: May 2028