Lunghezza-Guidonia doubling

Lunghezza-Guidonia doubling

This project includes a doubling of the Rome-Pescara line between Lunghezza and Guidonia, with an extension of about 10 kilometres, most of which will be constructed alongside the existing line.

There are also plans to upgrade the Bagni di Tivoli station, to build a new station in Collefiorito to replace the existing Guidonia Montecelio station, to install noise barriers and to eliminate level crossings along the section.

Vincenzo Macello was appointed Extraordinary Governmental Commissioner for completion of the works.

Advantages

  • An increase in capacity (from 4 to 10 trains/hour) with extension from Lunghezza to Guidonia of the metropolitan service with a 15-degree cadence.
  • Improvement of traffic regularity and optimisation of rolling stock management by increasing the number of tracks for parking with the new Guidonia Collefiorito location involving the elimination of currently-scheduled dispatches.
  • Improved accessibility thanks to road works, the elimination of level crossings and the construction of interchange car parks at Guidonia Collefiorito and Bagni di Tivoli.
  • Reduced travel time.
  • New spaces in the station of the new Guidonia Collefiorito locality.
140 km/h maximum speed
10 total kilometres
255 mln € in investments

Work progress status

  • Design
    Since 2008
  • Permits
    Since 2014
  • Tenders
    Since 2021
  • Start of work
    Since 2021
  • End of work
    Since 2023

Doubling Lunghezza - Bagni di Tivoli - Phase 2 Doubling Lunghezza - Bagni di Tivoli (civil works and technologies)

Stages of progression: WORKS 

  • Design end date: 2008*
  • End date of the authorisation process: 2014*
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2024
  • Activation date: 2024

*It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations.

Guidonia Collefiorito railway station - Phase 3 Guidonia Collefiorito railway station

Stages of progression: WORKS 

  • Design end date: 2008*
  • End date of the authorisation process: 2014*
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2024
  • Activation date: 2024

*It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations.

Bagni di Tivoli - Guidonia - Phase 4 and 5 (Bagni di Tivoli - Guidonia)

Stages of progression: DESIGN

  •  Activation: 2029