Brindisi – Airport railway siding

Brindisi – Airport railway siding

Information about the Brindisi - Airport Railway siding. 

The project has received complete public funding, including NRRP funds.

Roberto Pagone was appointed Extraordinary Governmental Commissioner for completion of the works.

100 km/h maximum speed
8 total kilometres
161 mln € in investments

Work progress status

Below are the details of the work progress for the Completion of the Brindisi - Airport railway siding.
*Data being updated
  • Design
    Since 2020
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work*
    Since 2023
  • End of works
    2026

Brindisi - Airport railway siding - Brindisi - Airport railway siding

Stages of progression: WORKS

  • Design end date: 2020
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Work end date: 2026
  • Activation date: 2026