Brescia-Verona-Padua

Brescia-Verona-Padua

This project foresees the construction of the new Brescia-Verona-Padua High Speed/High Capacity railway line, which is part of the Milan-Venice High Speed/High Capacity axis. This line is of strategic importance at both a national and European level. In fact, it is one of the elements of the Mediterranean Core Corridor that will connect ports in the south of the Iberian Peninsula to eastern Europe, passing through the south of France, northern Italy and Slovenia.

The project will increase the offer of high-speed, regional and freight transport along the horizontal Milan-Venice route, guaranteeing a better separation of traffic flows, with a consequent increase in the capacity and regularity of the service, a reduction in travel time and an increase in the frequency of trains.

Vincenzo Macello was appointed Extraordinary Governmental Commissioner for completion of the works

Advantages

  • The new HS/HC Brescia-Verona-Padua section will quadruple the current infrastructure allowing the transit of fast trains with a recovery of travel times between Milan and Venezia Santa Lucia of up to 10 minutes.
  • An increase in the capacity and regularity of traffic, also as a result of the specialisation of services (separation of traditional and High Speed flows), thus improving the regional transport system as well.
acav
250 km/h maximum speed
152 total kilometres
9,820 mld € in investments
A webcam in operation along San Martino Buon Albergo
HS/HC Brescia-Verona-Padua

Work progress status

  • Design
    Since 2014
  • Permits
    Since 2017
  • Tenders
    Since 2018
  • Start of work
    Since 2018
  • End of work
    Since 2026

Brescia East - Verona line - 1° Lot Brescia East - Verona line

Stages of progression: WORKS

  • Design end date: 2014*
  • End date of the authorisation process: for construction lots from2017 to 2019
  • Date of tender publication: 2018
  • Start date of executive design and implementation: 2018
  • Work end date: 2026
  • Activation date: February 2026

*DETAIL OF THE AUTHORISATIONAL PROCEDURE: July 2017 (Inter-ministerial Committee for Economic Planning Resolution 42 approval by the Definitive Project of the line and authorisation of the 1st Construction Lot). November 2019 (Inter-ministerial Committee for Economic Planning Resolution authorising the 2nd Construction Lot). THE DATE OF THE TENDER IS NOT APPLICABLE TO GC CONTRACTS: TAV-Iricav Due Convention of 15.10.1991 and successive Second Supplementary Agreement of 06.06.2018. 

Quadrupling at the eastern exit from Brescia - 2° Lot Quadrupling at the eastern exit from Brescia

Stages of progression: DESIGN

  • Activation date: december 2028

Access to Verona West - Junction AV/AC Access to Verona West

Stages of progression: TENDERS 

  • Design end date: 2021
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Activation date: May 2028

 

Access to Verona East - Nodo AV/AC Access to Verona East

Stages of progression: PERMITS 

  • Design end date: 2022
  • Activation date: december 2030

Verona - crossroad Vicenza - Verona-Padova: 1^Lot Verona - crossroad Vicenza

Stages of progression: WORKS

  • Design end date: 2015
  • End date of the authorisation process: 2018
  • Date of tender publication: 2020*
  • Start date of executive design and implementation: 2020
  • Work end date: 2026
  • Activation date: december 2026

*THE DATE OF THE TENDER IS NOT APPLICABLE TO GC CONTRACTS: TAV-Iricav Due Convention of 15.10.1991 and the successive Supplementary Agreement of 06.08.2020.

Vicenza crossing - Linea AV/AC Verona-Padova: 2^Lotto Funzionale: Attraversamento di Vicenza

Stages of progression: WORKS

  • Design end date: 2022
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023*
  • Start date of executive design and implementation: 2023
  • Work end date: 2032
  • Activation date: september 2032

*THE DATE OF THE TENDER IS NOT APPLICABLE TO GC CONTRACTS: TAV-Iricav Due Convention of 15.10.1991 and the successive Supplementary Agreement of 27.07.2023.

Vicenza-Padova - 3^ Lot Vicenza-Padova

Stages of progression: DESIGN

  • Activation: 2029

The definitive design has been financed and is currently under development.