<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=490038435288789&amp;ev=PageView&amp;noscript=1">

Brennero Base Tunnel

Brennero Base Tunnel

The Brenner Base Tunnel is the pivotal infrastructure project of the Scandinavian-Mediterranean TEN-T corridor, as it overcomes the natural barrier of the Alps and will reduce both the distance and journey time for rail transport between Innsbruck (Austria) and Fortezza (Italy). Passenger trains will be able to travel through the tunnel at speeds of up to 250 km/h. By eliminating the steep gradients, it will be possible for longer, heavier and more numerous freight trains to negotiate this section.

By reducing the steep gradients and thanks to the straighter alignment of the track – which is almost entirely free of bends – it will be possible to run longer and heavier trains. The new rail infrastructure will provide a viable alternative for freight transport and open up a whole new dimension of travel for passengers.

Advantages

  • Freight transport shifted to rail, thereby reducing traffic congestion to the benefit of the communities in the areas involved;
  • Ability for 740-metre-long freight trains to pass through without axle load restrictions, in accordance with the interoperability standards of the TEN-T Core Freight networks;
  • Increased rail capacity on the existing line between Fortezza and Brenner;
  • Adoption of all TEN-T standards, resulting in full interoperability between the countries concerned;
  • Protection against natural hazards;
  • Shorter journey times.
250 km/h maximum speed
64 total kilometres
8,8 mld € in investiment

Work progress

Below are the details of the work progress for the Brenner Base Tunnel.
  • Design
    Since 2013
  • Permits
    Since 2013
  • Tenders
    Since 2013
  • Start of work
    Since 2014
  • End of work
    Since 2028

Lot h21 - Gola del Sill

Stages of progression: WORKS

  • Design end date: 2019
  • End date of the authorisation process: 2019
  • Date of tender publication: 2019
  • Start date of executive design and implementation: 2020
  • Work end date: 2024

Lot h41 - Gola del Sill - Pfons

Stages of progression: WORKS

  • Design end date: 2020
  • End date of the authorisation process: 2021
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2021
  • Work end date: 2028

Lot h33 - Tulfes-Pfons

Stages of progression: DELIVERED

  • Design end date: 2013
  • End date of the authorisation process: 2013
  • Date of tender publication: 2013
  • Start date of executive design and implementation: 2014
  • Work end date: 2021

Lot h52 - Hochstegen

Stages of progression: WORKS

  • Design end date:  2021
  • End date of the authorisation process: 2021
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2023

Lot h53 - Pfons-Brennero

Stages of progression: TENDERS 

  • Design end date: 2022
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Work end date: 2028

Lot h61 - Mules

Stages of progression: WORKS

  • Design end date: 2015
  • End date of the authorisation process: 2015
  • Date of tender publication: 2015
  • Start date of executive design and implementation: 2016
  • Work end date: 2025

Lot h71 - Sottoattraversamento Isarco

Stages of progression: WORKS

  • Design end date: 2013
  • End date of the authorisation process: 2013
  • Date of tender publication: 2013
  • Start date of executive design and implementation:  2014
  • Work end date: 2023